What drawings do you need for a building permit?
The document checklist by project type — site plan, floor plans, elevations, sections, engineering, soil and energy reports — and the gaps that stall assessment.
A building permit is assessed from paper. If the drawings do not show something, the surveyor cannot assume it. Most of the waiting on a permit is not the assessment — it is chasing a document that should have been in the first email. What is needed depends on the project.
The full package: new homes and extensions
A new home, or an extension that adds habitable rooms, needs all of the following.
- Site plan. Boundaries and dimensions, the building’s position and setbacks, easements, the crossover and the stormwater point of discharge. To scale, with a north point.
- Floor plans. Every level, with room names, dimensions, wall types, window and door positions and smoke alarms.
- Elevations. All sides, with wall heights, floor levels, natural ground levels and the roof form.
- Sections. At least one cut through the building showing footings, slab, wall and roof construction and ceiling heights.
- Engineering. Footing and slab design, steel beams and lintels, bracing and tie-down, signed by the engineer.
- Soil report. The soil report sets the site class, and the slab and footings are designed to it. The engineering has to match it.
- Energy report. Habitable buildings need one — for a new home, a 7-star energy rating report — and it must match the drawings: the same windows, insulation and orientation.
- Specification. Materials, finishes and the standards the work is built to, where the drawings do not already say.
- Planning permit and endorsed plans, where the planning scheme calls for one — commonly an overlay, or more than one dwelling on the lot. The building permit has to be consistent with them.
- Title and plan of subdivision. These show the registered boundaries, covenants and easements. Building over an easement needs the report and consent of the authority it is vested in — usually council or the water authority, but it can be the sewerage, drainage, electricity or gas authority — and that consent has to be in hand before the permit can issue.
- Builder or owner-builder details. A registered builder’s registration number and, for a major domestic building contract, the insurance certificate — or an owner-builder’s certificate of consent from the Building and Plumbing Commission where the value of the work is above the Commission’s threshold.
Lots in a designated bushfire prone area add a BAL assessment. Extensions add the existing floor plan with the parts being removed marked.
Sheds, garages, carports and verandahs
A much smaller package — the same one we ask for on our shed and garage permits page. Most kit sheds come with the supplier’s engineering: elevations, sections, member sizes and footing or slab details, certified for a stated wind classification. Check that it covers your site — an exposed block on the edge of an estate can sit above the kit’s standard rating, and the supplier will issue site-specific engineering if asked.
To that you add a site plan showing the distance from the shed to each boundary and to the house, the title, and the address. A carport or verandah attached to the house also needs a detail showing how it fixes to the existing frame.
Retaining walls
An engineer’s design showing the wall type, footing, drainage and any load it carries from above — a driveway, a pool, a neighbour’s ground — plus a site plan with the wall’s line relative to the boundary and the ground levels on each side, and the title. Not sure the wall needs a permit at all? Our guide on when a retaining wall needs a building permit covers the height and boundary triggers.
Demolition
Less about drawings, more about consents: a site plan marking what is going and what is staying, with boundaries, neighbouring buildings and the street; a written demolition method and evidence the demolisher has the experience and equipment for it; engineering for whatever is left standing, if only part is coming down; any planning permit; and council’s Section 29A consent where the job triggers it. Abolishing the gas, electricity, water and sewer is not a document for the permit — but it runs on the distributors’ clock, so start early. Our demolition permit guide walks through the order, and our demolition permits page covers what the fixed fee includes.
When a marked-up aerial photo is enough
For a shed, carport or small outbuilding, you do not need a drafted site plan to start. An aerial photo with the structure drawn in and rough distances to the fences is enough for us to say whether it needs a permit, whether the siting works, and what the fixed fee will be. It is not enough to issue the permit: that needs a dimensioned site plan, which the shed supplier or a drafter can produce.
Common gaps that stall assessment
- The energy report was done on an earlier drawing and the windows changed since.
- Engineering designed for a different soil class, or no soil report.
- Kit shed engineering not certified for the site’s wind classification.
- No sections, so construction and ceiling heights have to be guessed.
- No title, so an easement under the garage turns up at the last minute.
- The drawings not matching the endorsed planning plans, or endorsed plans not supplied.
- The owner-builder certificate of consent not yet applied for. We cannot issue until it arrives.
- The surveyor appointment unsigned. Until the owner appoints us, we cannot start.
For the full new-home package and what happens after the permit issues, see our new home building permits page. Not sure what you have? Send it through the quote form — no drawings are required to ask — and we will list what is missing, once.